An intern is replacing a critical resource midway through a sprint. To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor. Two months later, the project goes into critical status, delaying the release milestone by a month.
What should the project manager have done to avoid this scenario?

الخيارات

  • A Requested an experienced resource as a replacement
  • B Convinced the critical resource to remain on the project
  • C Negotiated additional time to complete the project
  • D Allocated additional time for mentoring