اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 847 من 874

كل الأسئلة

A project manager is leading a project which shows a trend to exceed the cost baseline. What should the project manager do first to manage the budget?

الخيارات

  • A Inform the stakeholders that the project will be finished over budget.
  • B Ask the project sponsor for assistance in getting the budget back on track.
  • C Issue a change request including the analysis to increase the budget.
  • D Meet with the project team to analyze the actual cost to determine deviations.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.