A project manager works in an organization that wants to implement agile methods. Traditionally, the project progress was communicated via a weekly email to stakeholders. The development team uses a burndown chart and a kanban board to visualize progress.
What should the project manager do?

الخيارات

  • A Continue using only the traditional communication channels with external stakeholders.
  • B Provide access to the burndown chart and kanban board and ask stakeholders to use them.
  • C Organize training for all stakeholders on the burndown chart and kanban board.
  • D Use the burndown chart and the kanban board as an auxiliary communication channel.