A project team is working on an agile software development project. The project manager is concerned that the virtual team may not be as effective as a colocated team at headquarters.
Which two actions should the project manager leverage to ensure the team is meeting performance expectations? (Choose 2)

الخيارات

  • A Require a monthly individual status report
  • B Task functional managers to drive accountability
  • C Hold daily virtual meetings to review progress
  • D Utilize a web-based kanban board
  • E Implement time-keeping software for team members