During an iteration review session, some product features are at risk of being canceled due to high operational costs when the product is launched into a production environment. What type of analysis should the project lead have conducted to avoid this situation?

الخيارات

  • A Capacity analysis
  • B Gap analysis
  • C Risk analysis
  • D Benefits analysis