A key project team member is out on sick leave in the middle of a critical project iteration. The project sponsor learns that any delay with the end-of-iteration release will displease the business stakeholders. Although all team members are cross-functional, they are also working close to full capacity.
What should the project manager do to address this situation?

الخيارات

  • A Discuss this with the team so they are able to reprioritize critical tasks and aim for the release deadline.
  • B Discuss this with the sponsor and hold a meeting with the stakeholders so all of the team challenges can be shared.
  • C Discuss this with the team so they can complete the work of the unavailable team member and aim for the release deadline.
  • D Discuss the issues with the sponsor to fully convey the problem of the unavailable resource and the amount of work being done.