Travel restrictions are suddenly imposed during a project's execution. The team members reside in different geographic locations.
What should the project manager do next to address this issue?

الخيارات

  • A Place a hold on activities until the team can resume the work on-site.
  • B Ask the team members to proceed independently while examining needs and alternatives.
  • C Halt all processes until procurement and implementation of solutions are completed.
  • D Obtain and implement the sponsor's recommendations for a solution.