During the execution of a project, an experienced team member informs the project manager that they cannot take part in all of the scheduled project activities due to a conflicting operational schedule. What should the project manager do?

الخيارات

  • A Replace the team member with another available resource on the team.
  • B Discuss the situation with the team member's functional manager to see if the schedule can be adjusted.
  • C Check with the project management office (PMO) on the available resources to complete the activities.
  • D Encourage the team member to prioritize scheduled project activities.