اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 774 من 874

كل الأسئلة

During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?

الخيارات

  • A Create a reward system recognizing group contributions to get people motivated and improve performance.
  • B Facilitate sprint planning sessions with a focus on defining the minimum viable product (MVP).
  • C Promote a productive environment where everybody can work without interruptions from the rest of the team members.
  • D Design a set of metrics including velocity, which is a good measure of value delivered.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.