A new team member is added to a self-organizing team. The new team member is reluctant to speak and take part in team discussions or decisions.
Which two actions should the team take to engage this new team member? (Choose 2)

الخيارات

  • A Force the new team member to participate in activities that are considered easy.
  • B Report to the project manager about the new team member's behavior.
  • C Coach the new team member to improve engagement with the team.
  • D Facilitate an open discussion on all ideas and perspectives.
  • E Revisit the team's discussion on team behaviors and norms.