A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity.
How should the project manager deal with this request?

الخيارات

  • A Check the alternative resources available in the organization for the request.
  • B Evaluate the nature of the request and plan communication accordingly.
  • C Confirm that the budget and resources are available to execute the work request.
  • D Submit a change request and allocate the budget and resources needed for execution.