A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain.
What should the project manager do?

الخيارات

  • A Reduce the priority of project risks as all remaining risks are low-level.
  • B Notify stakeholders that all high-level risks have been resolved.
  • C Reclassify low-level risks as high-level risks.
  • D Reevaluate identified risks and update the risk register.