While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because of that, each feature is taking longer than initially estimated.
What should the project manager do to address the issue?

الخيارات

  • A Extend the dates for future project milestones.
  • B Initiate a change request to extend the project end date.
  • C Escalate the issue to the project sponsor.
  • D Address the issue during the next sprint planning meeting.