A team is the first team in the company to use agile methods for a traditional project. The team’s manager is concerned that the risks are not being managed.
What should the team do to assess and manage risks regularly?

الخيارات

  • A Focus on developing a working deliverable instead of documenting risks.
  • B Use regular feedback loops through daily standups, iteration demos, and retrospectives.
  • C Update the risk register during every iteration with any open concerns.
  • D Identify and escalate any identified risks to the facilitator to handle.