A project manager receives an email from a vendor stating that a shipment of computers is delayed for another week. As a result of this delay, the team reviews their schedule, alerts the department manager, and makes adjustments based on the new estimated delivery date.
Where should the project manager document these changes?

الخيارات

  • A Project team's website
  • B Vendor's website
  • C Company's external website
  • D Software manufacturer's website