A project manager leads a regulatory initiative with tight, non-negotiable timelines. During a status meeting, a key stakeholder asks if a critical milestone associated with the reporting functionality can be moved up by 4 weeks.

What should the project manager do first?

الخيارات

  • A Update the master schedule to reflect the reprioritized deliverables.
  • B Ask the team to work with the product owner to reprioritize the backlog.
  • C Gather additional information and ask the team to perform a root cause analysis.
  • D Request additional information and discuss the feasibility options and impacts with the team.