A large and complex project is comprised of multiple regions. The estimate to complete (ETC) work is assumed to be performed at the same cumulative cost performance index (CPI) as that incurred by the project to date. As of now, the earned value (EV) is 145 person/day, the planned value (PV) is 145 person/day, the actual cost (AC) is 170 person/day, and budget at completion (BAC) is 285 person/day.

What is the estimate at completion (EAC)?

الخيارات

  • A 315 person/day
  • B 334 person/day
  • C 310 person/day
  • D 285 person/day