السؤال 699 من 874

كل الأسئلة

A project manager is leading a diverse project team that includes new and experienced team members. A conflict has occurred between two team members. One team member prefers using digital tools for project communication. The other team member prefers in-person meetings and phone calls for communication.

What should the project manager do to manage this conflict?

الخيارات

  • A Allow the team members to continue using their preferred communication tools and methods.
  • B Instruct the team members to adapt to the project's communication tools and methods.
  • C Arrange a team-building activity to foster understanding and open communication among the team members.
  • D Initiate a conversation with the team members individually to understand their situations regarding communication.