A project manager is managing a project with a cost performance index (CPI) of 1.05 that is trending downward. To maintain on-time completion, the scrum master needs to add 30 additional team members in the next month to enable more sprints. The project manager is concerned because the schedule performance index (SPI) is 1.0.

What is the first step the project manager should take?

الخيارات

  • A Quantify the cost for the 30 team members and determine if there is budget available to fund the expanded team.
  • B Meet with the project team to forecast the SPI trend to determine if there are funds available to pay the 30 team members.
  • C Engage with the human resources (HR) representative to begin selecting candidates for the 30 open positions.
  • D Inform the project team that since the CPI is trending downward, there are funds available to expand the team.