اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 692 من 874

كل الأسئلة

A project is in the execution phase and there are disagreements between two key stakeholders about the project's scope. One stakeholder is adamant about expanding the scope and the other stakeholder is content with the current arrangement.

What should the project manager do?

الخيارات

  • A Schedule a one-on-one discussion with each stakeholder to understand their concerns.
  • B Schedule a meeting with both stakeholders to encourage dialogue and reach a decision.
  • C Suggest that the two stakeholders meet together to agree upon a project scope.
  • D Escalate the stakeholder's conflict to senior management so they can resolve the issue.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.