The project team members have finalized the technical specifications after their discussion with the machine manufacturers. However, it has been identified that the specifications are not aligned with the project management office (PMO). The project team members are confident about their choice of specifications.

What should the project manager do in this situation?

الخيارات

  • A Give approval of the technical specifications.
  • B Ask the sponsor for additional funding to hire a senior subject matter expert (SME).
  • C Request a decision from the project sponsor.
  • D Schedule a meeting with all of the subject matter experts (SMEs) to discuss.