A team has individual daily start times for each team member. Sometimes the overlap between team member working hours is short. During those times, the interactions and work as a team are reduced and ineffective.

What should the project manager do?

الخيارات

  • A Ask the team to start at the same time to obtain the maximum number of team working hours.
  • B Inform the team members who are joining late to join early and work together.
  • C Allocate the overlap time for each team member and ask them to adhere to the schedule.
  • D Ask the team to define a team charter and agree on core working hours.