A company is experiencing a high rate of rejected project deliverables. The project manager is requested to suggest a solution to improve quality. What should the project manager suggest?

الخيارات

  • A Break down the project into several iterations and incorporate a quality check by a quality auditor in each iteration.
  • B Request that all team members receive the newest quality standards training and review one another's work.
  • C Request that a quality specialist be assigned to the project to check the final product at the end of the project.
  • D Break down the project into several iterations and incorporate automatic testing and quality improvement sessions.