A project team member who has the expert knowledge necessary for the project is often absent from meetings. The team member sends a message to the project manager questioning them about the rationale behind some decisions made on the project.

How should the project manager handle the situation?

الخيارات

  • A Explain to the team member that it is mandatory that they increase their participation in project meetings.
  • B Inform the team member that decisions were already made and feedback should have been provided in the past.
  • C Add the team member's concerns to the risk register and discuss them during the next regular meeting.
  • D Schedule a meeting to review the team member's concerns and revisit the decisions if required.