A project manager is preparing a large and complex international project. In order for the team to work well together in a virtual environment, the project manager needs to set up ground rules for good communication.
What should the project manager do first?

الخيارات

  • A Develop the stakeholder analysis.
  • B Establish a communication channel.
  • C Distribute the risk register.
  • D Create a communication protocol.