A project manager notices that a team member is upset during a team meeting. The project manager assesses the situation and determines that the team member does not collaborate with some of the other team members.
What should the project manager do?

الخيارات

  • A Give some advice to the team member to reduce their stress and anxiety.
  • B Review team participation in the next retrospective meeting with all team members.
  • C Reach out to the team member to discuss and address their concerns as soon as possible.
  • D Evaluate upcoming project deadlines and reorganize team member assignments.