A project is nearing completion when a critical resource can no longer work on the project. A temporary replacement is brought in from an external company to take over the role; however, complaints are soon received from other team members about this person’s unprofessional conduct and behavior.
What should the project manager do first?

الخيارات

  • A Report the new team member to human resources (HR) for disciplinary actions.
  • B Hold one-on-one meetings with the new team member and the rest of the team members to align the team charter.
  • C Discuss the team charter with the new team member to align them with the agreed-upon conduct within the team.
  • D Ask the contracting agency to replace the temporary team member.