Developers spend most of the sprint writing code for user stories, leaving little time for testing. As a result, user stories cannot be tested in time and the stories remain unfinished by the end of the iteration, resulting in poor metrics.
What should the scrum master do first in this situation?

الخيارات

  • A Divide the user stories into two categories: development stories and test stories.
  • B Increase the number of developers on the team so stories are completed faster.
  • C Request the developers work overtime to ensure the testers have enough time to perform their tests.
  • D Revalidate the team’s velocity to ensure development and testing can be completed within the iteration.