In an ongoing project, there is an argument between two subject matter experts (SMEs) on what the correct approach to design should be. The project manager suggests that the two SMEs meet and come to a consensus.
Which conflict resolution approach did the project manager use?

الخيارات

  • A Collaborate
  • B Force
  • C Compromise
  • D Synergy