A project has obtained all of the necessary legal requirements and policies from the local government. During the execution phase, the product owner is informed that a new law impacting the project deliverables will be published within two weeks.
What should the project lead do?

الخيارات

  • A Work with the team to develop an alternative solution with no additional effect on the project’s budget.
  • B Review the product backlog items to evaluate the impact on scope and prioritize accordingly.
  • C Develop a change request for more resources and update the project budget and schedule.
  • D Ask the internal legal department to evaluate if the regulatory law could be managed internally.