اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 637 من 874

كل الأسئلة

A project manager is overseeing a 10-mile piping installation project that was supposed to spend US $15,000 per mile of piping installation and should complete the project exactly 20 weeks from its start. The project manager just found out that only 80% of the work has been completed.
What is the budget at completion (BAC)?

الخيارات

  • A US $300,000
  • B US $150,000
  • C US $100,000
  • D US $250,000

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.