اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 633 من 874

كل الأسئلة

The scope of a construction project that is being planned by a multinational company requires that services are procured via contract from an external provider. When considering communication channels, what should the project manager do to help maximize delivery success with this provider?

الخيارات

  • A Establish a common language of terms with which to communicate with the provider.
  • B Ensure that all project stakeholders participate in the scope definition meetings.
  • C Assign the project sponsor as the point of contact for all provider communication.
  • D Assign a project team member to document exchanged communication for future reference.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.