A team member on an important company project mistakenly caused significant cost overruns. The sponsor informed the project manager and expects the project manager to take action within 1 week. This team member has always been an outstanding performer.
What should the project manager do first to address the sponsor's concerns?

الخيارات

  • A Document the team member's mistake in the lessons learned.
  • B Talk with the team member to identify the reason for the mistake.
  • C Relocate the team member to another project due to the mistake.
  • D Train the team member to improve their performance to avoid future mistakes.