A project manager is working with a team that is demotivated and tired, as the project has been changing direction due to budget cuts from the sponsor. What should the project manager do first?

الخيارات

  • A Call the sponsor and ask for a meeting to clarify the scope before working any further on the project.
  • B Work with the team to understand what can motivate them to try and complete the project.
  • C Meet with the team to define together a plan that would help them deliver despite the budget cuts.
  • D Remind the team of their commitment with the client and the need to adapt to the client’s needs.