اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 610 من 874

كل الأسئلة

During a requirements review session with a customer, a team member gets upset when questioned by the customer and responds angrily. What should the project manager do next?

الخيارات

  • A Follow up with the whole team to find the best approach
  • B Discuss with the whole team the root cause of this issue
  • C Provide the team member with space to manage their emotions
  • D Meet with the team member to reset expectations

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.