A team member is not getting along with one of the project sponsors. The sponsor has requested to move the team member to another project. What should the project manager do next to resolve the situation?

الخيارات

  • A Hold a meeting with the team and explain the ground rules for the project.
  • B Meet with the team member and identify areas of improvement to satisfy the sponsor.
  • C Identify the reasoning behind the behavior of the sponsor and team member.
  • D Review the resolution of a similar past situation and apply the same strategy for the team.