A project to support an organizational transformation is in the planning phase. Transformation is the project sponsor’s idea and is not aligned with key stakeholders because they all have different opinions about the project outcomes. What should the project manager do next?

الخيارات

  • A Communicate project outcomes and results with the key stakeholders.
  • B Ask the project sponsor to help with engagement of the key stakeholders.
  • C Define a high-level project scope and share it with the key stakeholders.
  • D Conduct a workshop on project goals and deliverables with the key stakeholders.