A strategic project using international funds for a government agency is going through the execution phase. The government transition will take place in 1 month, and authorities will change. There is a risk that the project will be suspended or team members will be removed. The project manager wants to ensure that the project will continue despite these changes.
Which action should the project manager take to address this situation?

الخيارات

  • A Accept the risk as these changes are part of the organizational culture.
  • B Ask the sponsor to send a communication to the president-elect team with the progress of the project.
  • C Stop the project until the government transition has taken place.
  • D Ask the main stakeholders to document their progress on the project before the transition.