A project manager is leading a software development project. At the start of the project, the project team decides that iterations are the best way to run the project and deliver value to the customer more quickly.
Which three actions should the project manager take? (Choose 3)

الخيارات

  • A Develop the application as requested by the customer, based on the approved project requirements.
  • B Develop the application as requested by the customer, based on the approved project requirements.
  • C Facilitate a focus group to assess the functionality before development.
  • D Develop the project management plan based on the requirements requested by the customer.
  • E Use an agile approach to deliver the product based on sprints.
  • F Plan a minimum viable product (MVP) to get early feedback from the customer.
  • G Facilitate a focus group to assess the functionality before development.