A project with a geographically distributed team is ending its first iteration out of eight. During the daily meetings, the project manager realizes that some team members are not engaging in the discussion. What should the project manager do?

الخيارات

  • A Conduct a team activity to determine the reasons for this situation.
  • B Speak with the team to find a better time to hold the meeting.
  • C Update the risk log and follow the team members' performance.
  • D Ask the team members to speak during the meetings.