A government procurement team has been running a vendor selection process for more than 1 year, going beyond the originally planned 6 months due to a variety of factors. Two vendors have submitted proposals that were evaluated. The project manager asked for an estimated completion date 4 weeks ago, but it was not provided.
What should the project manager do?

الخيارات

  • A Ask the project sponsor to request an estimate from the procurement team.
  • B Escalate the delay issue to the project steering committee.
  • C Explain to the steering committee that vendor negotiations are unpredictable.
  • D Work with the procurement team to build a high-level timeline.