A multinational company is rolling out a new software platform within its subsidiaries. However, the distributed project team struggles to meet regularly. As a result, the project milestones are not being achieved.
What should the project manager do first?

الخيارات

  • A Inform the project sponsor and request additional team members to crash the project schedule to meet the target.
  • B Propose to roll out the new software in one subsidiary and then use the lessons learned to improve the project.
  • C Introduce an award system to promote member participation and establish some competition between the subteams.
  • D Evaluate the effectiveness of the virtual teams and support them with the necessary technology and equipment.