After the demo on a software project, one of the key stakeholders contacted the scrum master and complained that they were unaware of changes made to the project. After checking, the scrum master learned that the stakeholder’s details were incorrectly entered into the register.
What should the scrum master do?

الخيارات

  • A Check the stakeholder register and ensure that every stakeholder’s information is correct and current.
  • B Consider it a loss since the stakeholder should have ensured the contact information was up to date.
  • C Update the stakeholder’s information and inform them that they must make the team aware of any changes.
  • D Ask the product owner to update the stakeholders’ contact information at every meeting to address any changes.