A website application project is underway and the agile team has reached a stable velocity. After eight iterations, they complete 20 story points per sprint. The project lead and team plan to maintain the same velocity for the next 2 months. After this period, the team completed 100 story points. The project sponsor asks for the project status.
How should the project lead respond?

الخيارات

  • A The schedule performance index (SPI) is 25% less than expected.
  • B The cost performance index (CPI) is below average with a 25% reduction.
  • C The cost and schedule performance indicators are equivalent.
  • D The team’s performance indicator is higher than expected.