A project manager is leading a strategic and competitive advantage project for a healthcare organization that is in its testing phase. The team has been working on this project for 6 months, and the morale of the team is low due to the schedule.
What can the project manager do to motivate the team?

الخيارات

  • A Speak with the project management office (PMO) and request a 2-week extension of the schedule so the team can have rotational time off.
  • B Talk to the business team about the project phase and the team’s commitment, and request a monetary reward for the team.
  • C Meet with the horizontal team managers to recognize the team members and give rewards and promotions upon completion of the project.
  • D Continue to perform the last phase of the project with the project team as this will benefit the organization and provide a competitive edge.