During a review meeting, a team member informs the project manager about a recent regulation that requires a dual-verification process in the software. The project manager submits a version of the software that the project team created. However, the product sponsor strongly insists that there should be no updates to the software.
What should the project manager do?

الخيارات

  • A Collect the requirements of the regulation and follow the change control process.
  • B Include the new requirement in the next iteration without informing the sponsor.
  • C Release the software as is and start a new project to deliver the new requirements.
  • D Inform the team that the sponsor decided to reject any changes and release the software as is.