اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 546 من 874

كل الأسئلة

Due to contractual issues, a key team member cannot travel to the project location for a design review meeting. What should the project manager do?

الخيارات

  • A Ask the project sponsor if another team member can participate instead.
  • B Solve the contractual issues before continuing with the design review meeting.
  • C Consider setting up a virtual meeting with the team for the design review.
  • D Inform the stakeholders and demand an immediate solution from the project sponsor.

النقاشات