اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 539 من 874

كل الأسئلة

A project manager is working on a project to develop a new watch at a matrix organization. Which two key items should the project manager include in their feedback to external stakeholders? (Choose 2)

الخيارات

  • A Schedule performance index (SPI) for the portfolio
  • B Expected return on investment (ROI) for portfolio projects
  • C Earned value in terms of schedule
  • D Earned value in terms of resources
  • E Earned value in terms of cost

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.