اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 535 من 874

كل الأسئلة

A team decides to adopt an agile approach for their new project. During a sprint, the project manager realizes that there is a need to show progress and optimize the collaboration among teams.
Which tool should the project manager use?

الخيارات

  • A Kanban board
  • B Gantt chart
  • C Daily meetings
  • D Retrospective meetings

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.