اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 534 من 874

كل الأسئلة

During a final investment decision meeting, all of the stakeholders were aligned on the project benefits, proposed budget, and schedule. Before final approval was given, the executive requested an aspirational target for the project team to obtain an enhanced benefit from the project.
What should the project manager do in this situation?

الخيارات

  • A Accept the request and commit to some benefit improvement opportunities for the project.
  • B Explain the planning and budgeting process and demonstrate that the project proposal maximizes benefits.
  • C Investigate the request and express willingness to find ways to obtain higher project benefits.
  • D Review the proposal and suggest optional benefit improvement opportunities for the project.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.